From CAD User Mechanical Magazine Vol 13 No 08 - SEPTEMBER 2000
The Channel Tunnel Rail Link, the £5.2 billion project to design and construct the Channel Tunnel Rail Link (CTRL)
CTRL is being designed and project managed by the
Rail Link Engineering (RLE) consortium
comprising Bechtel, Arup, Halcrow and Systra. RLE manages
the contractors who are building the railway on behalf of client
Union Railways. It will be opened in two
sections, the first in 2003 between the Channel Tunnel and Fawkham
Junction, in north Kent where it will connect with the existing
Railtrack network en route to Waterloo International Station.
Subsequently, Section Two will run beneath the Thames and through
east London to St Pancras, scheduled for completion in 2007.
A design team led by Alan
Price, the Section One Lead Design and Construction Engineer, used
Intergraph's Civil suite to create the alignments for the route
between Fawkham Junction and the Channel Tunnel, a distance of 78
kilometres (46 miles). He said: "We
undertook the work using all three Intergraph Civil products:
InRail for the track, InRoads for the earthworks
and in other areas such as mitigation
earthworks and road earthworks we have used SiteWorks.
"All the products are sub-sets of each other
with InRail having all the functionality at the top end. Once the
alignment for the CTRL is fixed by the trackwork team it is cascaded
down to the civil, structural and environmental engineers.
"They are using our geometry strings to
generate all their earthworks and construction
plans," added Mr Price who is also responsible for the Railtrack
interface works. The interface is complicated
because the CTRL weaves in and out of Railtrack assets.
During construction of Section One, existing signalling, track and
power supplies have to be modified while keeping the existing service
running.
Managing change control
One of their challenges is to manage
change control. Mr Price said: "For
example, if someone designs a culvert and asks for the alignment
to be raised slightly to accommodate the
new design, we use [the software] to work out what the implications
are in the context of high speed alignment geometry rules.
"If you lift the high speed alignment in
one place, that has implications over several kilometres.
It can involve changes to the track bed and amending the design
of several bridges, too. In such cases it often makes sense
to ask for the culvert design to be changed instead."
A change to the alignment has to be signed off by all disciplines
before it is incorporated into the master alignment by the trackwork
team.
Mr Price, who advised
CTRL consortium members Ove Arup on the choice of technology, says
they adopted Intergraph software for the CTRL project because
it is flexible and works directly on top of the MicroStation CAD
package, removing the need to import and translate data. This means,
for example, that when architects produce CAD files for station
layouts they can be used as a reference to snap
to within InRail. An alignment can be offset from a particular
structure by points picked in the graphics without having to rely
on translations going backwards and forwards.
Although a lot
of CTRL alignment involves plain line design, the software's capability
is vital at junctions. For example, where the track
branches off into Ashford Station a grade separated junction is
required: in other words the tracks have to cross over without coming
into contact. This will be achieved with elevated track at one end
of the station and an underpass at the other end. "Without
designing in three dimensions achieving the correct structural clearances
everywhere would be a very complex process," said Alan Price
"When you have to create new geometry in this context, the
functionality of InRail is very powerful. You can just bolt
bits together and move bits around until
they are right."
The freight problem
Although the main usage of the CTRL will be by
high speed international and domestic trains it has also been designed
to accommodate freight. This has been a major challenge for
the CTRL. Alan Price explains: "No other high speed line
anywhere in the world caters for freight in this way. It means
that we need to design for high speed passenger
traffic running at 300km an hour while
the freight is supposed to run at 140km an hour. "The
difficulty is that if you cant the track for a high speed use, you
are going to get a lot of wear on the low rail when the freight
train rides around it with a higher axle load at a much lower speed,
thus increasing maintenance."
The challenge is to "ensure
that, by having to cant for the high speed trains, you have not
exceeded the criteria for the slower speed ones". InRail
allows you to do this. Mr Price explained: "You can create
a series of cant profiles for a single horizontal alignment and
say "This is what we want to apply if we run at 300 kph and
this is the cant we want to apply if we run at 140kph".
Then you work out what the optimum is between the two and
fix it. "You can generate the cant information and plot
profiles for both speeds automatically."
A lot of alignment optimisation was also carried out as a result of close community liaison and trying where possible to address local residents' concerns and environmental criteria on Section One. Mr Price said: "We needed to be in a position to make changes such as lowering an embankment or moving or increasing mitigation earthworks to reduce noise levels. The advantage… was that you could look at all the constraints on screen and move the alignment around until you got what you wanted. "Happily, you can turn alignment changes around very quickly. InRail, InRoads and SiteWorks applications have been invaluable in meeting the tight time-scales required for the infrastructure design on this prestigious project." CU
For more information
contact: www.integraph.com ©2006 BTC. All rights reserved.Case Study
Click here for a Print Friendly Version
The products referenced in this site are provided
by parties other than BTC. BTC makes no representations regarding either the
products or any information about the products. Any questions, complaints,
or claims regarding the products must be directed to the appropriate manufacturer
or vendor. Click here for usage
terms and conditions.
For Comments towards this website please contact the webmaster
No part of this site may be reproduced without written permission of the
owners.
www.CADUser.com